Project / Construction Management

Project

Technical consultant for the management and construction of the Olympic Village, Greece

 
 
Location: Greece
Client: Olympic Village S.A.
Date: 2001-2005
Construction costs: approx. € 360 million
Technical Details

Site 1 250 000 m², residential area with 2 300 apartments. Post-Olympic adaptation into a residential area for 10 000 inhabitants. Athletic installations, 3 schools, 2 office buildings, fire-fighting station, church, polyclinic, commercial centre and 650 000 m² city-park.

OBERMEYER’s assignment embraces the provision of engineering services in both the design and the tender phase. The section has a total of 40 km tracks, 12 new bridges, 4 new tunnels, 25 existing bridges and 10 existing tunnels, all partly constructed, which require checking and optimization, two stations and 3 stops. The project adheres to the EU interoperability requirements and designs are according to the relevant both Macedonian and European regulations. The tender process to select a contractor for works and services ensures compliance with EBRD’s Procurement Policies and Rules; Works Contract is under FIDIC rules. Site 1 250 000 m², residential area with 2 300 apartments. Post-Olympic adaptation into a residential area for 10 000 inhabitants. Athletic installations, 3 schools, 2 office buildings, fire-fighting station, church, polyclinic, commercial centre and 650 000 m² city-park.

Services Provided

Total project and quality management, time and cost control, design checking, site coordination and organizational consulting on behalf of the Client

Surveys:

  • Geodetic (topographical) surveys
  • Geotechnical Surveys

Design:

– Detailed design for all Civil Works (substructure, superstructure, structures)

  • alignment – substructure
  • railway superstructure
  • bridges
  • tunnels
  • overpasses/underpasses
  • retaining walls, culverts
  • drainage
  • formation setting
  • railway stations and halts, including buildings, platforms, and canopies etc.
  • disposal sites / borrow pits
  • expropriations
  • Design of signalling and telecommunication systems

– Design of electrification system

– Technical Specifications for Interlocking and Communication Equipment.

– Electrification Design

Tender Documents:

  • Technical part (arising from the approved designs)
  • Legal part: Procurement Plan, Tender Documents, Prequalification Documents, Evaluation Reports, Special Conditions of FIDIC Contract